Japanese Consortium to Operate Dhaka Airport's Third Terminal

GreenWatch Desk: Aviation 2026-11-23, 8:18pm

images8-2b7dfb86c066c512c82a09e0249ca9181795443646.jpg

Third terminal of Hazrat Shahjalal International Airport



A Japanese consortium will operate and maintain the third terminal of Hazrat Shahjalal International Airport in Dhaka for 15 years under a proposed concession agreement with the Civil Aviation Authority of Bangladesh (CAAB).

The government will receive an upfront payment of $8.1 million, equivalent to around Tk 100 crore, along with a stipulated share of revenue from passenger and cargo handling.

The proposal to sign a concession agreement with the Japanese consortium was approved at a meeting of the Cabinet Committee on Economic Affairs on Monday (November 23). Finance Minister Amir Khasru Mahmud Chowdhury chaired the meeting.

Led by Sumitomo Corporation, the consortium includes several Japanese public and private entities, including Japan Airport Terminal Co., Narita International Airport Corporation, Nippon Koei and Sojitz Corporation.

The agreement will be implemented under the public-private partnership (PPP) framework.

Under the proposed terms, Bangladesh will receive either 27 per cent of total passenger-handling revenue or $2.10 per passenger, as applicable. For cargo handling, the government will receive either 27 per cent of total revenue or $11.50 per metric tonne.

The agreement also provides for an embarkation fee of $12.50 per passenger. The fee currently stands at Tk 500 in local currency.

According to relevant sources, after the Japanese consortium submitted its financial proposal for operating the third terminal, Invest Bangladesh reviewed it and completed negotiations. The proposed agreement was subsequently finalised after vetting by the Legislative and Parliamentary Affairs Division and obtaining opinions from the Finance Division and the National Board of Revenue (NBR).

The agreement also includes provisions for ground-handling operations. Biman Bangladesh Airlines will handle up to 50 per cent of ground-handling services for international airlines.

Full-scale operations of the third terminal must begin within 14 months of the project's handover.

One of the key conditions stipulates that international flights will stop operating from the first and second terminals once the third terminal becomes operational.

Another condition bars the opening of any new airport within a 100-kilometre radius of Hazrat Shahjalal International Airport during the 15-year contract period.

However, Hajj flights, chartered flights, budget airlines and domestic flights will continue to operate from the first and second terminals.

According to CAAB data, the first and second terminals of Hazrat Shahjalal International Airport currently have an annual passenger-handling capacity of around eight million.

The third terminal will add another 12 million passengers to that capacity, bringing the airport's total annual handling capacity to approximately 20 million.

The estimated cost of the Hazrat Shahjalal International Airport expansion project is Tk 22,213.09 crore.

Launched on July 1, 2016, the project is scheduled for completion by June 30, 2027.