Nepal Disaster and Hydropower

How Global Banks Downplayed Risks they Knew

Disasters 2026-08-29, 11:17pm

rescuers-pull-china-nepal-border-flood-survivors-from-mud-b0e286147db75f09bccf13ccc2c6464d1788023853.jpg

Rescuers pull China-Nepal border flood survivors from mud.



By SANDRP on August 29, 2026

On the 28th August 2026, Nepali officials roughly doubled their tally of missing people to over 1,900, saying hydropower producers had only recently shared a count of unaccounted-for workers at projects in the devastated river valleys. It is feared that over 900 people are missing from hydropower projects.

This might be a watershed moment for the disaster-torn hydropower boom in South Asia, funded many times by International Financial Corporations and Multilateral Banks like ADB and World Bank.

Hundreds of hydropower labourers, engineers and locals are currently trapped inside tunnels of projects like Upper Trishuli 1 and Trishuli 3A which is funded by a loan from China’s Eximbank in the flood ravaged Nepal. More than 350 have been rescued by the valiant efforts of Nepal Army, but many more are still trapped inside the tunnel, including Indians.

214 MW Upper Trishuli I is one of Nepal’s largest hydropower project, nearly complete, which now lies nearly destroyed by the sheer force and fury of the Himalayan Floods. The entire Trishuli Basin has dense hydropower development.

As rescue work progresses and disturbing images arise, this may not seem to the time to raise the issue of Hydropower in Himalayas. But it is. Because as we will see, reports and reminders about the repeating floods in Trishuli River, like other Himalayan rivers, made no difference to the builders, or the funders. Climate disasters associated to infrastructure across Himalayas have been causing deaths and destruction with a despairing regularity. They are repeatedly putting thousands of labourers, local residents and tourists in mortal danger, with very little recourse and accountability.

The Multilateral Development Banks including the ADB and the World Bank Group’s IFC, that financed and championed the Upper Trishuli-1 hydropower project and conducted a Cumulative impact Assessment of Trishuli Basin were acutely aware of the extreme danger to which they were exposing thousands of laborers and officials. Their own reports repeatedly highlighted it. But they did not ask for stringent checks and balances, for further studies or measures like Early Warning Systems. Funding was sought and provided in the garb of “Climate and Disaster Resilience”. Impacts from Tibet were not studied, funding did not stop. Thousands of labourers, engineers and contractors were thus concentrated in a volatile valley which suffered serious floods in 2024 and GLOF floods 2025, apart from current flood.

International Finance and Trishuli/ Bhote Koshi Disaster

The $647.4 million Upper Trishuli-1 (UT-1) hydropower project, which is now more than 90% damaged and where hundreds are trapped, is one of the largest foreign direct investments in Nepal’s history, a characterization International Finance Corporation’s (IFC) own press release uses when describing the project.

It is bankrolled and owned by a consortium of the world’s most powerful financial institutions. The (IFC) (the private sector arm of the World Bank) led the effort to arrange the project’s $453 million debt package and it owns a 15% equity stake in the project company, making it a co-owner. The Asian Development Bank (ADB) and the Asian Infrastructure Investment Bank (AIIB) put a combined $150 million in loans into the dam. The ADB drew half of its funds from Canadian Climate Fund specifically meant to “build disaster resilience”, something that sounds especially harsh today. The remainder of the debt package came from a web of development finance institutions spanning from the UK (CDC Group, now British International Investment) to South Korea (Korea Development Bank, Export-Import Bank of Korea) to the Netherlands (FMO) and the OPEC Fund.

Asian Development Bank: Warnings from its own report ignored

ADB states that the Upper Trishuli 1 project supports ADB’s strategies: “tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability” [13]. Under ADB’s support, the project received a loan from the Canadian Climate Fund for the Private Sector in Asia II (CFPS II) for USD 30 million.

The ADB acknowledges: “Climate change risk assessment previously concluded that the risks of climate change impacts on the project are low; however, extreme rainfall in previous years and a glacial lake outburst flood event in 2025 resulted in damage to some project facilities while under construction and significant alteration of river morphology along the Trishuli river”

In fact, the Independent Panel of Experts (IPoE) Report in June 2025 specifically stated: “IPoE had recommended the preparation of a Climate Resilience Assessment for the Project. This assessment has yet to be done. Following the September 2024 event, which showed that combinations of climatic and geological events can have severe consequences, we recommend expanding the scope of such climate resilience assessment to disaster risks” [14]. No such Climate Resilience Assessment is present on the dashboard.

The ADB was aware not only of the 2025 flood at the hydropower project, but a September 2024 flood also. The IPoE Report states: “The September 2024 floodwater surge close to Project headquarters threatened the stability of the Powerhouse labor camp putting workers at risk and requiring temporary doubling-up of workers.”

It points out:

“The slow implementation of a reliable early flood warning system, as discussed in the Environmental section of this report, remains a major risk to those project communities in proximity to the river, especially Mailung and Gumchet, considering the damage inflicted in the Powerhouse area by an isolated floodwater surge in September 2024.”

The IPoE Report for December 2024 outlines the September 2024 flood event that “washed away the labours camp” and mentions “The Owner’s Engineer estimates the return period of the September 28th flood to 4 years, while the EPC’s main subcontractor estimates it to 10 000 years (!)”

This was followed by a 2025 flood event in the same ravaged Trishuli region. This flood made 10 projects defunct. The ADB Dashboard does not include any reports of this flood.

No funding stopped. The International Agencies involved which have the financial wherewithal and available expertise did not push for In-situ early warning system or a Climate Risk Assessment Plan even after repeated floods and risks. Being an international body themselves, they did not see the need for pushing for a trans-boundary risk assessment for this project, so close to the Tibet border.

International Finance Corporation (IFC):

The IFC published a Cumulative Impact Assessment of Trishuli Basin in 2020 to fulfil its own lending conditions. The report came out 7 years after the Uttarakhand disaster where thousands of Himalayan pilgrims died in a devastating flood triggered by a GLOF and complicated by hydropower. IFC CIA had the opportunity and space to address cumulative disasters, GLOFs, transboundary impacts, growing footprint of a changing climate. It did nothing. While not discussing cumulative threats of GLOFs and flood disasters, it did not even attempt to look at upstream Tibetan impacts. It made no combined disaster plan for the entire basin littered with hydropower projects.

At the same time, the Independent Panel of Expert Reports which reported to ADB were also reporting to the IFC which means it was aware of the recurrent floods, GLOFs and warning about Climate Resilience Assessment and Early warning systems. Yet, nothing changed.

China’s Exim Bank

China’s Export Import or Exim Bank provided $149 Million concessional loan for Trishuli 3 A Hydropower project which is seevrely damaged and in whose tunnels hundreds of workers are trapped. The Contractor for the project was Chinese China Gezhouba Group Company. They have no independent, binding environmental safeguards and rely on Host Country rules or voluntary action at best! This is despite the fact that China and Nepal, share the most fragile parts of this transboundary basin.

Recent Hydropower Disasters in Himalayas

In August 2026, 10 labourers died in flooding accident in India’s 444 MW Vishnugad Pipalkoti Project

In July 2026, 25 labourers died in Sikkim’s Teesta VI Hydropower Project

In August 2025, thousands of people were affected by floods made worse by a Ranjit Sagar hydropower Project in India

In October 2023, more than 55 people died in Teesta III collapse following a GLOF which was forecasted.

In Feb 2021, more than 50 people died, many of whom were labourers in Rishiganga HEP in India

It is with this background that communities living in Sikkim Himalayas are asking for a moratorium on hydropower projects which lead to concentration of people and impacts in the highly vulnerable Himalayas. Multilateral Development Banks, International Climate Funds, International Finance Corporations need to appreciate the “International” nature of trans-boundary disasters and growing climate risks. It is high time International Finance Corporations like ADB, IFC, AIIB etc., accept their role in putting people and ecosystems at risk. Especially the migrant labors working in hydropower industry in Himalayas, who are some of the most tragically vulnerable sections of our society.

Himalayan rivers have been witnessing tragedy after tragedy. Let us hope that this a watershed moment where lasting change begins.

Parineeta Dandekar, Himanshu Thakkar, SANDRP