Dhaka Metro rail: Last segment of MRT-6 line installed Thursday

Transportation 2022-01-27, 8:42pm

metro-rail-train-trial-run-on-dec-12-2021-4de8451a660ed743395f0feea884e9fc1643294536.jpg

Metro rail train trial run on Dec 12 2021



Dhaka, Jan 27 – Bangladesh’s first metro rail on a 20.1 km-route from Uttara to Motijheel became completely visible on Thursday after installation of the last girder of the viaduct. 

The installation was completed at 11.14 am on Thursday when workers successfully put the last span of the viaduct between the pillars no 582 and 583 in front of Jatiya Press Club. 

MAN Siddique, managing director at Dhaka Mass Transit Company Ltd (MRT) was present virtually during the installation work. 

The overall progress of the Metro Rail is now 74 per cent, officials said. 

The original length of the metro rail route was 20.1 km from Uttara to Motijheel, but it has now been extended by 1.16km to Kamalapur Railway Station. - UNB