Barapukuria 525MW Power Plant shut down for mechanical fault

Power 2025-02-20, 9:20am

barapukuria-coal-based-525mw-power-plant_11zon-2b8781629df9776a228a7182b5499d031740021632.jpg

Barapukuria coal-based 525MW power plant - UNB



The Barapukuria Power Plant in Dinajpur has completely shut down operations due to multiple mechanical failures, including a boiler leakage, officials said on Wednesday.

Abu Bakkar Siddique, chief engineer of the plant, said, "Since this is a mechanical issue, it is difficult to specify when operations will resume. The necessary equipment for repairs is being procured domestically," he said.

According to him, all three units of the 525MW plant have been shut down due to different technical problems. Unit 1 (125MW) suffered a boiler pipe leakage yesterday, while Unit 3 (275MW) faced a pipe and bearing failure on February 15.